An executive can approve a recovery decision in two minutes when a project status report makes the risk, consequence, and required action unmistakable. Many reports fail this test. They list completed tasks while hiding forecast slippage, unresolved dependencies, and decisions that will soon become irreversible.
This guide provides a one-page executive project status report template and a detailed weekly version, complete with worked examples, 32 reporting fields, RAG status rules, financial indicators, escalation triggers, and a repeatable reporting workflow. Both formats help project managers turn routine updates into faster decisions, stronger accountability, and more predictable delivery.
1. What Should a Project Status Report Include?
A project status report summarizes delivery performance against an approved baseline and identifies the actions required to protect project objectives. Its purpose is to give stakeholders enough reliable information to understand progress, evaluate emerging problems, and make timely decisions.
A useful report answers five questions:
Are we still likely to deliver the agreed scope by the committed date and budget?
What changed since the previous reporting period?
Which milestones, dependencies, or risks threaten delivery?
Who owns the recovery actions, and when must they be completed?
What decisions or support are required from stakeholders?
These questions connect directly to project governance responsibilities, project management reporting tools, RACI responsibility mapping, and earned value management analysis.
Executive reporting versus weekly project reporting
The executive version should fit on one page. It prioritizes business consequences, delivery forecasts, significant exceptions, and decisions requiring management authority.
The weekly version serves project managers, workstream leaders, and delivery teams. It includes completed deliverables, upcoming activities, milestone changes, risks, issues, resource constraints, and detailed action ownership.
Both versions should draw from the same underlying project records.
If an integration delay appears as critical in the weekly report, the executive report should reflect its effect on the milestone forecast. Different reporting audiences may receive different levels of detail, but the factual position should remain consistent.
This principle matters in program management, senior project management consulting, PMO leadership, and executive project management careers.
Five reporting rules that prevent misleading updates
1. Report the forecast alongside the baseline. A delivery date remains meaningful when readers can see both the original commitment and the current expected outcome.
2. Distinguish completed work from activity. "Conducted three vendor meetings" describes effort. "Approved the integration specification and closed six acceptance defects" describes progress.
3. Separate risks from issues. A risk concerns an uncertain future event. An issue has already occurred and requires management. Both should have owners and response plans.
4. Attach decisions to deadlines. An unresolved approval becomes a project threat when the latest safe decision date passes.
5. Make every status rating explainable. A green indicator should be supported by evidence. A red indicator should identify the consequence, recovery action, and responsible authority.
These rules are especially important when AI-generated project updates summarize large volumes of activity, predictive analytics tools estimate future outcomes, and project management integrations consolidate data across systems.
The following 32-field HTML template establishes which information belongs in each reporting format and what makes each field actionable.
| Reporting Field | One-Page Executive Version | Weekly Project Version | Reporting Rule / Trigger |
|---|---|---|---|
| 01. Project identification | Project name and unique ID. | Project name, ID, program, and workstream. | Use consistent identifiers across reporting systems. |
| 02. Reporting period | Report date and data cutoff. | Exact start and end dates for reporting week. | Separate reporting cutoff from distribution date. |
| 03. Executive sponsor | Named accountable sponsor. | Sponsor and delegated decision authority. | Identify who can authorize escalated actions. |
| 04. Project manager | Name and contact details. | Name, workstream leads, and reporting owners. | One person accountable for integrated report accuracy. |
| 05. Overall RAG status | Green, Amber, or Red with justification. | Overall rating with supporting workstream ratings. | Apply documented thresholds consistently. |
| 06. Status movement | Improved, unchanged, or deteriorated. | Previous and current ratings with change drivers. | Explain every material rating change. |
| 07. Executive summary | Two or three sentences on delivery and decisions. | Detailed explanation of current progress and constraints. | Lead with consequences and management action. |
| 08. Business objective | Expected business outcome and value. | Requirements and deliverables supporting the outcome. | Escalate changes undermining approved benefits. |
| 09. Scope performance | Scope status and significant changes. | Approved baseline, additions, removals, and rework. | Distinguish approved changes from unauthorized expansion. |
| 10. Schedule health | Major forecast date and delivery confidence. | Task dependencies, slippage, float, and milestones. | Compare current forecast against approved baseline. |
| 11. Baseline completion date | Original approved delivery commitment. | Baseline dates for all significant milestones. | Preserve original baseline history. |
| 12. Forecast completion date | Current evidence-based delivery forecast. | Forecasts by milestone and critical workstream. | Investigate forecast movement beyond tolerance. |
| 13. Milestone performance | Three most consequential milestones. | Complete milestone register with owners and dates. | Flag missed acceptance or decision gates. |
| 14. Progress completed | Major accepted outcomes this period. | Verified deliverables and completed work packages. | Count accepted outputs rather than reported effort. |
| 15. Planned next steps | Next major deliverable or executive checkpoint. | Named weekly deliverables with due dates. | Every commitment needs an owner and acceptance criterion. |
| 16. Budget at completion | Approved total project budget. | Baseline budget by workstream or cost category. | Use the current approved budget baseline. |
| 17. Actual costs | Total actual cost to report date. | Actuals and committed expenditure by category. | Distinguish accounting actuals from committed costs. |
| 18. Forecast final cost | Estimate at completion and forecast variance. | Forecast method, drivers, assumptions, and sensitivities. | Explain expected overruns before funds are exhausted. |
| 19. Cost performance index | CPI only when meaningful and reliable. | Earned value, actual cost, and calculation details. | Investigate CPI below agreed tolerance. |
| 20. Schedule performance index | SPI or equivalent progress measure when applicable. | Earned value, planned value, and milestone evidence. | Use critical-path dates alongside SPI. |
| 21. Critical risks | Top two or three exposures and business impact. | Risk IDs, likelihood, impact, triggers, and owners. | Escalate risks nearing their activation deadlines. |
| 22. Active issues | Issues threatening delivery commitments. | Issue IDs, severity, recovery owners, and due dates. | Separate existing problems from potential events. |
| 23. Dependency health | Dependencies needing management intervention. | Supplier, approval, resource, and technical dependencies. | Flag unverified commitments affecting the critical path. |
| 24. Resource capacity | Material staffing constraint, if any. | Allocation, shortages, availability, and substitutions. | Escalate critical skill gaps before milestone failure. |
| 25. Quality performance | Acceptance or critical defect status. | Defect severity, test results, rework, and exit criteria. | Do not report complete until acceptance is verified. |
| 26. Change requests | Material approved or pending changes. | Change IDs, scope, cost, schedule effect, and status. | Never silently incorporate pending change requests. |
| 27. Decisions required | Specific executive decision and deadline. | Decision register with options and recommendation. | State consequences of missing the decision deadline. |
| 28. Corrective actions | Major recovery action and accountable owner. | Action IDs, owners, due dates, and completion evidence. | Track overdue actions independently of narrative status. |
| 29. Stakeholder readiness | Material adoption or approval concern. | Training, communications, and sign-off status. | Escalate readiness gaps before go-live. |
| 30. Benefits realization | Expected value and changes to the business case. | Benefits assumptions, leading indicators, and ownership. | Flag delivery choices that reduce planned benefits. |
| 31. Reporting evidence | Links to approved dashboards or source records. | Schedules, finance records, logs, and supporting files. | Ensure important statements are traceable. |
| 32. Next reporting date | Next sponsor checkpoint. | Next weekly cutoff and publication deadline. | Maintain a predictable reporting cadence. |
2. One-Page Executive Project Status Report Template + Completed Example
Executives need a concise explanation of whether the project is achieving its intended outcome, what could prevent delivery, and which decisions require their authority.
A one-page report works best when information is arranged in descending order of decision importance.
The recommended sequence is overall status, executive narrative, delivery forecast, financial exposure, major risks, decisions required, and next milestones.
This structure supports executive project management, COO-level operational oversight, project governance leadership, and portfolio-level PMO reporting.
Copy-ready one-page executive report structure
Project: [Project name and identifier]
Reporting date: [Date and data cutoff]
Sponsor: [Name] | Project manager: [Name]
Overall status: [GREEN / AMBER / RED] | Previous status: [Status]
Executive assessment: [Two or three sentences describing delivery confidence, material changes, consequences, and the highest-priority management action.]
Delivery commitments: Baseline finish [date]; forecast finish [date]; schedule variance [days]; major scope changes [summary].
Financial position: Approved budget [amount]; actual cost [amount]; forecast final cost [amount]; anticipated variance [amount].
Top delivery exposures: [Risk or issue ID, consequence, accountable owner, and recovery deadline.]
Decision required: [Exact approval requested, recommended option, financial impact, and latest safe decision date.]
Next milestones: [Milestone, baseline date, forecast date, and readiness condition.]
Next review: [Date] | Supporting evidence: [Dashboard, schedule, risk register, financial record.]
Keep detailed task lists, meeting minutes, and routine team activities in the weekly report. The executive page should emphasize material exceptions and decisions.
Completed one-page executive status report example
The following example uses a fictional customer portal upgrade. All figures and dates are illustrative.
Project: Northstar Customer Portal Upgrade | NS-042
Reporting cutoff: November 20, 2026
Sponsor: Chief Operating Officer | Project manager: Digital Delivery Lead
Overall status: AMBER (previously GREEN)
Executive assessment: Three of four major integrations have passed acceptance checks, and the migration rehearsal reconciled all critical records. The remaining API gateway failed its performance requirement, delaying integration acceptance. The December 18 go-live commitment remains recoverable if additional specialist support is authorized by November 23; without recovery, the current planning forecast is December 23.
Schedule: Baseline go-live December 18; current unmitigated forecast December 23, three working days later.
Budget: Approved budget $240,000; actual costs $144,000; earned value $132,000; current performance-based final cost estimate approximately $262,000, indicating a potential $22,000 overrun.
Critical issue: I-007, API gateway throughput failed acceptance testing. The accountable integration lead is coordinating remediation and a November 24 retest.
Decision required: Approve up to $8,000 in additional specialist support by November 23 to accelerate remediation. This optional expenditure is excluded from the $262,000 performance-based forecast and requires separate financial assessment.
Next milestone: Integration acceptance, originally November 19, now provisionally forecast for November 27, dependent on successful retesting.
Next review: November 27, 2026.
This example provides an executive with a decision, cost exposure, deadline, and potential business consequence in a compact format.
It also shows why a missed technical acceptance milestone can be red at workstream level while overall project status remains amber under an approved policy that recognizes a credible recovery path.
Use the RACI matrix generator to distinguish the integration owner's responsibility from the sponsor's funding authority. Validate the financial forecast through earned value management techniques, then place the unresolved acceptance condition within the project's governance escalation process.
How to write an executive summary that gets decisions
An effective summary follows three linked statements:
What changed? Identify the material deviation since the last reporting period.
What does it threaten? Quantify the effect on delivery, cost, quality, compliance, or benefits.
What happens next? State the proposed response and the latest safe decision date.
For example:
"API performance testing missed its approved throughput target, delaying integration acceptance. The December 18 release is exposed to a three-working-day slip. Sponsor approval of specialist recovery support is required by November 23."
This structure makes project risk escalation, program management decisions, stakeholder accountability, and executive oversight easier to manage.
3. Weekly Project Status Report Template: What to Include Every Friday
A weekly status report connects completed deliverables, current problems, upcoming commitments, and measurable changes in project performance.
Unlike the executive version, it should preserve enough operational detail for team leads to identify exactly what requires attention.
The weekly report should also make changes visible between reporting periods. An unresolved dependency that appears in five consecutive reports without an escalating response indicates ineffective control.
This matters particularly in Agile project delivery, digital project management, marketing project management, and international development projects, where distributed responsibilities make routine reporting important.
Copy-ready weekly project status report structure
Project and reporting period: Identify the project, reporting week, manager, and distribution date.
Overall status and movement: State the current RAG rating, previous rating, and reasons for change.
Completed this week: Record accepted deliverables, milestone achievements, completed testing, approved decisions, and measurable progress.
Planned for next week: Identify deliverables, accountable owners, due dates, and completion criteria.
Milestones: Show baseline dates, current forecasts, dependencies, and schedule movement.
Financial performance: Include approved budget, actual costs, commitments, financial forecast, and material variances.
Top risks: Report the most significant uncertain events, leading indicators, preventive actions, and responsible owners.
Active issues: Identify problems already affecting the project, corrective actions, escalation requirements, and expected resolution dates.
Dependencies: Document supplier commitments, external approvals, technical interfaces, and critical resource availability.
Decisions and support needed: Specify the required authority, recommended choice, due date, and consequence of delay.
Action tracker: Carry forward incomplete actions with stable identifiers and revised dates.
Evidence and approval: Link source records, identify the report reviewer, and confirm the next reporting cutoff.
These sections can be maintained using project management templates, reporting integrations, AI-supported documentation workflows, and project governance controls.
Completed weekly project status report example
Project: Northstar Customer Portal Upgrade
Week ending: November 20, 2026
Overall status: AMBER, deteriorated from GREEN.
Completed this week
Completed the first migration rehearsal with 100% reconciliation of designated critical records and 99.8% reconciliation of other records against an approved 99.5% threshold.
Accepted three of four major system integrations.
Completed user acceptance testing preparation for account management and customer notification workflows.
Verified role ownership for deployment, rollback, and operational handover.
Planned next week
November 23: Complete specialist recovery approval and revised integration plan.
November 24: Retest the API gateway against the required 500-transactions-per-second performance target.
November 25: Validate test evidence and update the release readiness assessment.
November 27: Seek integration acceptance, conditional on required performance and quality results.
November 30: Begin user acceptance testing if the integration gate is approved.
Milestone variance
Integration acceptance originally due November 19 is now provisionally forecast for November 27.
The release baseline remains December 18, but the unmitigated schedule forecast has moved to December 23. Recovery activities are being evaluated before a formal rebaseline decision.
Financial position
Approved total budget: $240,000.
Actual cost to date: $144,000.
Earned value: $132,000.
Planned value: $150,000.
Cost performance index: 0.92, rounded.
Schedule performance index: 0.88.
Performance-based estimate at completion: approximately $262,000, assuming current cost efficiency continues.
The proposed $8,000 specialist recovery option requires separate authorization and is not included in that estimate.
Critical issue
I-007: The API gateway failed its 500-transactions-per-second performance requirement during the November testing cycle.
The integration lead owns remediation and must present verified retest results by November 24.
Material risk
R-014: If the revised integration solution fails performance testing, release readiness may remain below the approved entry criteria, causing additional delay.
The release manager is preparing recovery options and updating milestone forecasts.
Decision required
Approve or reject additional specialist recovery capacity, capped at $8,000, by November 23. The sponsor must also confirm the funding treatment before any commitment.
Next reporting date: November 27, 2026.
This example illustrates how a delivery team can preserve traceability between the weekly report, executive summary, issue register, and financial forecast.
Three details that make weekly reports substantially more useful
Maintain previous forecasts. A project that repeatedly moves its completion date by three days may appear stable if reports show only the latest date. Preserve historical forecasts to reveal cumulative slippage.
Separate task completion from acceptance. Development can report a feature as finished while quality assurance still identifies blocking defects. Use accepted deliverables as the stronger completion measure.
Use stable action identifiers. Every major action should retain an ID across reporting periods. Changing the wording of an overdue action should never erase its original deadline.
These practices strengthen project manager career capabilities, PMO reporting standards, predictive analytics quality, and project delivery accountability.
Select your biggest reporting weakness to receive a specific corrective action that can improve your next project status report.
4. Project Status Report RAG Indicators, KPIs, and Forecast Calculations
A status report becomes misleading when green, amber, and red represent personal opinions instead of agreed criteria.
A project manager may describe a milestone as green because the team is working hard. Another may classify it as amber because the forecast has moved outside the agreed tolerance.
Both judgments cannot be meaningfully compared unless the organization defines how status is determined.
Define RAG status using project-specific thresholds
A practical illustrative framework is:
GREEN: On track. Current evidence indicates that approved commitments remain achievable within agreed tolerances. Major controls are operating and critical decisions are current.
AMBER: At risk. One or more commitments are threatened, but an achievable recovery option remains available within the project's decision and resource constraints.
RED: Critical or off track. A critical commitment has failed, or the forecast cannot be recovered within approved tolerances without a major intervention, exception, or revised baseline.
These definitions need additional rules for severe safety, security, regulatory, and contractual exposures.
A low financial variance should never conceal a serious unresolved compliance failure.
Apply these rules through a formal project governance framework, establish decision ownership using the RACI matrix generator, and connect schedule and cost performance to an earned value management framework.
Use five measurable indicators instead of unsupported confidence statements
1. Forecast milestone variance
Calculate the difference between the approved baseline completion date and current forecast completion date.
For the illustrative Northstar project, December 18 is the committed go-live date and December 23 is the unmitigated forecast, a delay of three working days under the example calendar.
2. Cost performance index
CPI = Earned Value / Actual Cost.
For Northstar:
CPI = $132,000 / $144,000 = 0.92, rounded.
A CPI below 1 indicates that earned value is lower than actual expenditure for the work measured.
3. Schedule performance index
SPI = Earned Value / Planned Value.
SPI = $132,000 / $150,000 = 0.88.
This shows less budgeted work has been earned than was scheduled by the reporting cutoff. SPI is an earned-value progress indicator and should be interpreted alongside actual milestone dates and critical-path analysis.
4. Estimate at completion
One commonly used performance-based forecasting approach is:
EAC = Budget at Completion / CPI.
EAC = $240,000 / (132,000 / 144,000) = approximately $261,818.
This method assumes that cumulative cost efficiency continues. Changes in future staffing, procurement, scope, or recovery spending can produce different forecasts.
5. Variance at completion
VAC = Budget at Completion − Estimate at Completion.
VAC = $240,000 − $261,818 = approximately −$21,818.
The negative value indicates an expected overrun under the stated forecasting assumption.
For a deeper analysis, use the earned value management calculator, explore predictive analytics in project management, and assess advanced project governance approaches.
Keep financial forecasts separate from unapproved recovery options
Suppose the project manager proposes an additional $8,000 for specialist recovery.
That proposal requires a clear financial classification.
If the expenditure is newly identified, not committed, and excluded from the current EAC, management should see the $262,000 performance forecast separately from the potential additional cost.
A simple additive scenario would produce approximately $270,000, assuming the entire $8,000 is incremental and cost performance otherwise remains unchanged. A fully evaluated recovery forecast should also reflect any savings, productivity improvements, or changed remaining-work assumptions.
This distinction prevents double counting and makes executive financial decisions, program-level funding reviews, project controls reporting, and senior consulting recommendations more defensible.
Report leading indicators alongside results
Lagging indicators tell the organization what has already happened.
Leading indicators identify conditions that may damage future outcomes.
Examples include repeated integration test failures, supplier inspection delays, unresolved design assumptions, rising defect escape rates, and decreasing availability of critical specialists.
For software implementations, automated checks may reveal increasing defect rates before user acceptance deteriorates.
For construction projects, verified supplier production progress may indicate a procurement delay before delivery dates move.
For distributed programs, decision turnaround times may reveal governance weakness before schedule variances become visible.
These signals become especially valuable when combined with project management cybersecurity analysis, predictive project analytics, API and integration management, and international development project coordination.
The report should identify which early-warning thresholds require intervention and which person is authorized to act.
5. How to Automate and Improve Weekly Project Reporting Without Losing Accuracy
Preparing the same report every week can consume valuable delivery capacity when project managers manually collect information from schedules, spreadsheets, communication tools, and vendor updates.
Automation can reduce collection and formatting effort, provided the organization maintains clear source ownership and controls.
The most effective workflow uses one reliable project dataset to produce both executive and weekly reporting views.
Step 1: Establish the source of truth
Select the authoritative system for each type of information.
Schedules may come from the maintained project plan. Financial figures should be reconciled against approved accounting or project controls data. Risks and issues should use formally maintained registers.
Workstream leads should confirm milestone completion and acceptance rather than relying exclusively on automatically closed tasks.
Maintain data cutoff dates and version history.
This approach supports project management API integrations, digital project management operations, PMO reporting governance, and AI-assisted reporting workflows.
Step 2: Introduce a fixed reporting timetable
A practical weekly cycle might follow this sequence:
Wednesday: Workstream leads validate milestone progress, new risks, and required decisions.
Thursday morning: Finance, procurement, and technical owners reconcile their current data.
Thursday afternoon: The project manager challenges inconsistent statuses and confirms material forecasts.
Friday morning: The weekly report is published with the agreed reporting cutoff.
Friday afternoon: The executive version is distributed, supported by direct escalation where urgent decisions are required.
Where a critical event occurs between reporting cycles, management should receive immediate escalation rather than waiting for the next scheduled update.
A standardized cadence supports global project leadership, digital nomad project management, freelance Agile delivery, and project governance coordination.
Step 3: Automate collection before automating judgment
Automated reporting can reliably retrieve dates, owners, status changes, cost figures, open defects, and overdue actions when source systems are properly configured.
More caution is required when systems automatically determine whether a project is healthy.
A schedule may show many completed tasks while a single unresolved critical-path dependency threatens the entire launch.
Similarly, an AI summary may emphasize activity volume without recognizing that acceptance testing failed.
Use automation for evidence collection, change detection, formatting, and first-pass narrative drafting. Require accountable human review of significant forecasts, RAG ratings, and proposed decisions.
Develop this capability through practical AI reporting workflows, AI automation analysis, project cybersecurity management, and predictive analytics applications.
Step 4: Check the report for five high-cost errors
Before publication, confirm the following:
Baseline integrity: Have current forecasts been presented separately from approved baseline dates?
Financial consistency: Are actual costs, commitments, EAC, reserves, and proposed recovery spending appropriately distinguished?
Risk transparency: Have significant risks and active issues been represented accurately, with owners and deadlines?
Decision completeness: Does every important request specify the authority, recommended action, consequence, and latest safe decision date?
Narrative consistency: Does the overall RAG rating agree with the underlying evidence and the organization's approved escalation rules?
These checks reduce misleading updates in executive program reporting, senior project consulting, financial performance control, and stakeholder governance.
Step 5: Measure the effectiveness of reporting itself
A project reporting process should improve delivery decisions.
Track how long it takes to publish an accurate report after the data cutoff, how many significant inconsistencies are identified during review, and how often executive decisions arrive after their latest safe date.
Also monitor the percentage of high-priority corrective actions completed on time and the frequency of unexpected major milestone deterioration.
When stakeholders repeatedly receive accurate warnings but fail to act, the organization has a governance problem that requires escalation redesign.
When stakeholders receive inaccurate forecasts, investigate source data, reporting definitions, and assurance controls.
When reports are accurate and timely but ignored, reduce unnecessary detail and make the required decisions more prominent.
These distinctions help address project management burnout caused by ineffective coordination, project manager career resilience, PMO leadership effectiveness, and senior executive project accountability.
6. FAQs About Project Status Report Templates
-
An executive report concentrates on overall delivery confidence, material exceptions, business consequences, and management decisions. It should typically fit on one page.
A weekly project report includes the operational details needed to coordinate execution, including accomplishments, upcoming deliverables, risks, issues, dependencies, owners, and deadlines.
Both should use consistent source data and reporting cutoffs.
For more advanced applications, explore project governance reporting, program management oversight, project management templates, and executive project leadership.
-
A moderately complex project may require one to three pages for its main weekly narrative, with detailed logs maintained separately.
The appropriate length depends on decision complexity, audience, project size, and reporting obligations.
A weekly report should enable the team to identify material changes and required actions without searching through extensive activity descriptions.
For large programs, supporting schedules and registers can be attached or linked.
Use PMO operating practices, reporting integrations, and RACI ownership tools to maintain detail without overwhelming the primary report.
-
The essential measures depend on the project's objectives, but common indicators include milestone variance, forecast completion date, cost variance, quality acceptance, critical risk exposure, and overdue corrective actions.
Projects using reliable earned value data may also report CPI, SPI, EAC, and VAC.
Select indicators based on their ability to reveal future delivery problems and support management decisions.
Explore the earned value management calculator, predictive project analytics, project governance practices, and project management reporting resources.
-
Green generally indicates delivery remains achievable within approved tolerances. Amber signals threatened commitments with credible recovery options. Red indicates critical failure or forecast outcomes requiring significant intervention.
Organizations should establish objective thresholds for schedule, cost, scope, quality, safety, and compliance.
The status definitions should also specify mandatory escalation conditions and authority for exceptions.
Link the rating system to project governance, earned value management, stakeholder responsibility mapping, and program oversight.
-
Yes. Risks describe uncertain future events, while issues describe conditions that have already occurred.
The executive report should highlight the few exposures requiring attention. The weekly version should provide IDs, severity, owners, response actions, and relevant dates.
A materialized risk may become an issue while additional uncertainty remains in the risk register.
This separation improves cybersecurity project oversight, complex integration management, governance accountability, and predictive risk reporting.
-
Yes. Cost and schedule measure different dimensions of project performance.
A project may remain within approved spending limits while a critical supplier delay threatens its delivery date.
Similarly, it may be on schedule but forecast to exceed its cost baseline.
The overall status should follow agreed aggregation and escalation rules, with significant exceptions clearly explained.
Use earned value management calculations, project governance controls, executive management reporting, and program management practices to distinguish different performance dimensions.